Northgate Groundbreaking Friday

Northgate is ready to start digging, wooooo

Northgate Link Extension groundbreaking and community celebration
August 17, 2012
3:30 pm – 7:30 pm
Groundbreaking ceremony-3:30 to 4:30 p.m.
Community kick-off celebration-4:30 to 7:30 p.m.
Location: Former QFC site at N.E. 66th Street & Roosevelt Way N.E.

When that TBM finally breaks through I’ll breathe a sigh of relief. The festival sounds like a good time for the kids — if Roosevelt Station were already open, I’d probably head up there with mine.

About Martin H. Duke

Martin joined the blog in Fall 2007 and became Editor-in-Chief in 2009. He is originally from suburban DC, but has lived in the Greater Seattle area since 1997. He lives with his family in Columbia City and splits his work time as a Communications Engineer between the Eastgate area and Tukwila.




Comments

  1. When will they actually start digging the tunnels?

    • David Seater says:

      Very soon. Demolition work is already underway in Roosevelt, starts later this fall in the U District.

    • Pete Lorimer says:

      According to documents on the ST website (most recent I could find are dated May 2011) show tunneling from Roosevelt to U District to begin in early 2013 and go through mid-2017, and tunneling from the Portal to Roosevelt would be early 2014-Second half of 2018. A separate document shows U District to University of Washington Station (Husky Stadium) tunneling would be from early 2014 through early 2017.

      • You have bad links. The latest APR shows tunnel boring to be from Sep 2014 to Jul 2015.

      • Pete Lorimer says:

        Ugh. I was going to go to the Progress Report, but saw that ST had seperate PDFs for each of them and linked there instead. I hate when outdated info is still on the documents section and not archived and replaced with more up-to-date info.
        Though the referenced Progress Report shows three different sets of dates:
        The Project Schedule on report page 28 (pdf page 24) shows N125 Combined Tunnels (UW- N Portal) going from Jan 8, 2013 – Mar 8, 2018
        The Construction Schedule Highlights on report page 32 (pdf page 28) says TBM Tunnels Notice to Proceed given in Aug 2013 with Substantial Completion in Mar 2018
        And finaly, the Critical Path (same page) shows only the Roosevelt – University tunneling from Sep 19, 2014 – Jul 13, 2015

      • Oops, I was just looking at the critical path chart, so it was just a subset of the full contract.

      • yeah, my impression is that the groundbreaking on Friday is ceremonial, and that the digging contracts for north link go out to bid in early 2013. It will be quite a while before any dirt is actually moved.

  2. Woo Hoo, start the countdown timers again. Northgate only 3,285 days away.

  3. Brian in Seattle says:

    This is great news..!!

  4. Matt Johnson says:

    I’ll be there!

  5. Tim Whittome says:

    I plan on being there. I was at the Mercer Street celebration last night at the SLU Discovery Center and was able to thank Senator Murray for all she does for our state. Did you know that she made sure that TIGER grants made it into the stimulus?

    Anywa, good job on Mercer opening in two weeks and let’s move forward with the west side and finish off the remaining parts of the east end of it.



You may want to read our comment policy.